Leadership teams know this in principle. The test is whether supply contracts are set up so that evidence is produced, checked and accepted at the right moments rather than reconstructed at the end.
What NCL’s consultant did on a major decommissioning facility
On a major decommissioning facility, NCL’s consultant oversaw the supply of about £40m of plant and equipment as the project’s nuclear safety champion, owning the quality plans, the inspection hold points and manufacturer acceptance. The facility is operational.
The example puts quality plans, hold points and manufacturer acceptance under one role. That principle of clear ownership applies on any nuclear supply programme.
Where acceptance comes unstuck
Acceptance criteria written after manufacture has started are a familiar source of trouble. If the supplier does not know, when the order is placed, which records and test results you will need to accept the item, you are unlikely to receive them in a usable form.
Hold and witness points that are written down but not resourced are another. The two are different. A hold point stops work until it is released by the authority named in the agreed inspection and test plan, which may be the purchaser, its representative, a third-party inspector or the licensee. A witness point gives the named party the opportunity to attend, and work can usually proceed as the plan allows once proper notice has been given. When a hold point’s release authority is unclear or unavailable, the hold still preserves control, at a price: work waits, and schedule and possibly cost absorb the delay. The risk to control comes when that pressure leads people to relax holds informally.
The third is unclear accountability. Engineering owns the specification, procurement the contract, quality the audit and the site team receipt. Acceptance crosses all four, so accountability for it needs to be explicit across those functions, with each hand-off defined.
For a UK licensee, these arrangements support licence compliance. Licence Condition 17 requires management systems which give due priority to safety, and Licence Condition 6 requires adequate records to demonstrate compliance with the licence conditions, and their preservation. Acceptance evidence for items important to safety can become part of that record. Not every item carries the same weight: controls should be proportionate to the safety significance of what is being bought, which is where effort is best concentrated.
Building acceptance into the order
Acceptance is more dependable when it is designed into the contract rather than negotiated at delivery. The quality plan, and the inspection and test plan with its hold and witness points, should be agreed before manufacture begins and form part of the order. The records, certificates and test results needed for acceptance, and the format they must take, should be listed at the same point.
Each hold point needs a release authority defined in the plan, with cover arranged so that release does not depend on one person’s availability. Early surveillance, such as a first-article inspection, can find problems while they are still cheap to correct. Concessions need firm control: each accepted deviation should carry a recorded technical justification, with its safety implications assessed in proportion to the significance of the item. And provenance deserves the same scrutiny as dimensions and test results, because material certificates and traceability records are part of the evidence too.
What leadership can check quickly
A managing director can learn a lot from one request: a current, consolidated view of the safety-significant items on order, showing each item’s next hold point, its date and its release authority. If that view cannot be produced readily, it is worth checking who owns acceptance and how the records are kept. It is also worth knowing how many concessions are open and who approved them, and whether any equipment has arrived without complete acceptance records.
The harder question is how accountability for acceptance is assigned across engineering, procurement, quality and site. A committee or a department can hold it, provided the accountability and the hand-offs between functions are explicit.
Where supplier certification fits
ONR’s technical assessment guide NS-TAST-GD-077 covers supply chain management arrangements for the procurement of nuclear safety related items or services. ISO 19443:2018 sets quality management requirements for organisations supplying products and services important to nuclear safety. Certification gives buyer and supplier a common language. It does not transfer the purchaser’s responsibility for confirming that the evidence meets its requirements, and the licensee still has to be satisfied.
Acceptance on nuclear projects
Equipment acceptance draws on quality, engineering and safety judgement together. The case above appears on NCL’s Decommissioning practice page, and independent assurance more broadly sits within our Safety, Regulation and Assurance practice. On a project with safety-significant items on order, the acceptance arrangements are worth testing before the first hold point falls due.